All dates are subject to change As of 18, February 2010
| Traffic Impact | Date |
|
SB I-95 Lane Re-Alignment (Beltway IL, Ramp D):
Ramp lane of SB I-95 Local will be "EXIT ONLY" to SB Telegraph Road (Exit 176A); merge with CD lane will be relocated to a point on SB I-95 prior to the Cameron Run bridge.
|
February 19, 2010 |
|
Detour of Ramp from NB I-95 to NB Telegraph Road (Ramp A) (Begin duration of MS #5 & MS #6):
Ramp bridges over Telegraph Rd and I-95 to be demolished (Ramp A), ramp traffic to be detoured using the old ramp to Exit 176A (former Ramp H), then turning left at the signal onto NB Telegraph Rd. Temporary signal to be activated on NB Telegraph Rd at Pershing Avenue.
|
Early March 2010 |
|
NB I-95 Shift (VB-2/3/6, Beltway OL):
Three lanes of NB I-95 traffic will be shifted to the right up to the Cameron Run bridge.
|
March, 2010 |
|
Opening of Ramp from NB Telegraph Rd to Eisenhower Avenue (VB-2/3/6, Ramp A-2) (completion of MS #5):
Ramp from NB Telegraph Rd to Eisenhower Avenue to be opened. Closure of access from NB Telegraph Rd to Pershing Avenue. Removal of temporary signal on NB Telegraph at Pershing Ave.
|
Early Summer 2010
(4 months after MS #5 begins)
|
|
Opening of Ramps from NB I-95 to NB Telegraph Rd and Eisenhower Avenue (VB-2/3/6, Ramp A, Ramp A-1) (completion of MS #6):
Ramps from NB I-95 to NB Telegraph Rd and Eisenhower Avenue to be opened. Closure of former Ramp H..
|
Fall 2010
(8 months after MS #6 begins)
|
|
Opening of Ramp from SB Telegraph Rd to SB North Kings Hwy (VB-2/3/6, Ramp H-4):
Ramp from SB Telegraph Rd to SB North Kings Hwy to be opened. Left turns to be prohibited from SB Telegraph Rd at the intersection with North Kings Hwy. Signal to be re-activated on Ramp H-1 at the intersection with SB Telegraph Rd.
|
Spring 2011 |
All dates are subject to change due to weather or other construction activity delays
|